Project Details
- Client
Coffey International
- End User
PetroChina
- Catagory
Oil & Gas
- Date
October 2014 – August 2015
- Status
- Delivered

Working through Coffey International, GRG provided an environmental risk assessment, developed an environmental emergency response plan and cost benefit analysis for Petrochina’s Halfaya field and operations.
Deliverables included:
- Environmental Risk Assessment
- Oil Spill Response Gap Assessment
- Crisis and Emergency Response Document Assessment
- Environmental Emergency Response Plan
- Oil Spill Response Equipment Requirements and Specifications
- Oil Spill Response Cost Benefit Analysis
- Feed Package for ESIA
The Challenge:
Working in the environment of post-war Iraq pulling together response capabilities of a pre-war system and the emerging modern operations of PetroChina in an extremely rural section of northern Iraq.
The Result:
All components delivered and accepted by both Coffey International and end user PetroChina. Project delivered on budget.
$100k
Project Value
100%
Delivered
Images © PetroChina, Reuters & GRG. You are not authorized to use any of the images shown on this page.
Other GRG Projects

Oil & Gas
Puma Energy

Crisis Management
Dubai Supply Authority DUSUP

Oil & Gas